Alright, you guessed it! It’s time to revisit our master schedule and see how the projects are coming along. Now, originally we scheduled out our planned projects on a monthly basis. When I went to take a look at it, I’m not going to lie, it was eye-opening . We’re not terribly ‘behind’ per say, but things are definitely taking longer than anticipated (which is more the rule than the exception, I’m learning).
When I went to update it for what we’ve done and have yet to do and re-schedule out some projects, it just didn’t feel right. We pretty much work on things as we decide we want to and are able, so it’s silly to try and over-exert ourselves because we scheduled something to be done. Also, we’ve done some re-arranging on the order of things. For instance, we started the half bath reno (which wasn’t scheduled to begin until May 2015). And we may push off kitchen plans until some other rooms are more completed.
When re-thinking this schedule, I decided it made more sense for our renovation process and my well-being to create a by-room to-do list rather than a month-by-month projection. I kept it high level on projects that are still pretty far out and added more in-depth details on rooms that I have a clearer vision for. So, without further ado, our November Master Project List.
Whole House
Prep for flooring- Install flooring on first level
- Install baseboard on first level
- Install flooring on second level
- Install baseboard on second level
- Upgrade door trim
- Upgrade window trim
Den
Remove popcorn ceilingPrime and paint panelingPaint windows- Add sectional
- Add TV and console
- Add curtains
- Add art/decor
- Add lighting
- Clean sliding door and replace door handle
Half Bath
- Tile in marble subway tile
- Paint/stencil in imperial trellis pattern
- Add board and batten
- Install vanity
- Install toilet
- Add mirror
- Add light fixture
- Install bathroom fixtures (toilet paper holder/towel ring)
Guest Bedroom
Install overhead light fixturePaint- Paint window
- Finish closet
- Trim/paint around bed area
- Add bed
- Add curtains
- Add nightstands
- Add art/decor
Master Bedroom
- Install overhead lighting
- Paint
- Paint windows
- Add crown molding
Office Bedroom
Install overhead light fixturePaintPaint windows
Halls/Stairway
- Install flooring on stairs
- Install toekicks and trim
- Paint
- Paint balusters
- Update upstairs lights
- Update first floor lights
- Add art/decor
Kitchen
- Knock down wall and bulkhead
- Move gas line
- Install cabinets
- Install appliances
- Install countertop and sink
- Paint
- Install hardware
- Add backsplash
- Add bar stools
- Update light fixtures
Living Room
- Add furniture
- Add crown molding (?)
- Add couch
- Add chairs/benches/side tables
- Add lamp lighting
- Paint
- Trim out entrance
- Add art/decor
Dining Room
- Refinish curbside table
- Paint
- Paint windows
- Floor
- Baseboard
- Art/Decor
Full Bath
- Replace tub base
- Tile shower surround
- Tile floor
- Paint
- Install vanity
- Install toilet
- Install mirror & light fixture
- Install bathroom fixtures (towel bar/toilet paper holder/storage shelves?)
It’s fun to see some items being checked off the list already. I think the hardest part sometimes is just getting started. Once the ball is rolling on a few projects you finally feel like you are getting somewhere and there is a end goal in sight 🙂 Hopefully we’ll be able to check off a few more of these items by the end of the month! And with this format, I won’t be scared to check in every month with y’all and discuss our progress. Are you more of a time based scheduler or a to-do-list maker?